The short answer

Look after the injured person first: first aid and 999 if needed. Make the area safe and stop work there. Record what happened while it's fresh, then check whether it's reportable under RIDDOR: deaths and specified injuries must be reported without delay, over-7-day injuries within 15 days. Tell your insurer, then the client.

  1. Hour 0–1: people first. First aid, 999 if in doubt, make the area safe, stop work there. Then record it: accident book, photos, witness names.
  2. Hour 4–24: the RIDDOR test. Death or specified injury: report without delay (phone 0345 300 9923 is allowed for these). Off work over 7 days: report within 15 days. Over 3 days: record it.
  3. Tell your insurer early and follow the policy's notification terms. Employers' liability cover must be at least £5 million.
  4. Facts only. Don't guess the cause, admit fault or promise money on the day.

A shout from the scaffold, then silence. Someone is on the ground. In the next hour you'll make decisions that matter for that person, for your business and for anyone who asks later what happened.

Most of what ranks for this is written by injury-claim solicitors for the person who got hurt.

This guide is for the UK builder or contractor running the site. It covers what to do after an accident on site in the first hour, 4 hours and 24 hours, by the HSE's own rules. Want your site set-up checked? Book a free strategy call.

This is general information from a contractor's experience, not legal advice. For your situation, speak to a health and safety adviser or a solicitor.

1Step 1 of 5

Hour 0 to 1: people first

  • First aid now. Your first aider or the nearest trained person takes charge of the injured person.
  • Call 999 if in doubt. Send someone to the gate to meet the ambulance.
  • Make the area safe. Stop work in that area, isolate power or plant, cordon it off.
  • Leave things as they are where it's safe to: the ladder, the tool, the board. They show what happened.
  • Tell the person's family if they can't, or if they ask you to.
2Step 2 of 5

Hours 1 to 4: record it while it's fresh

Memories change within days. Write everything down today.

Record How Why
Accident book entryDate, time, place, person, what happened, injury, first aid givenOver-3-day injuries must be recorded; it's the start of your file
PhotosWide shots and close-ups of the area, equipment, conditions, before anything movesShows the scene as it was
WitnessesNames, phone numbers, a short written account from each, signed and datedPeople leave sites and forget
The workWhat task, which method statement and risk assessment, what equipment and PPEYou'll need it for RIDDOR, the insurer and any HSE visit
StatusEmployee, self-employed sub, agency worker or member of the publicDecides who reports and which insurance responds
Hard hat and tools in a red site box
Keep the equipment involved aside and labelled once the area is safe. It's part of the record.
From Sviat

Firefighting the same problems every week? Take the free 4-minute Construction Business Scorecard: 18 questions on your pipeline, sales, pricing, cash flow and systems, with your weakest area shown first.

3Step 3 of 5

Hours 4 to 24: the RIDDOR test

RIDDOR is the law on reporting serious workplace accidents to the HSE. Work through it in this order.

What happened What you must do Deadline
A deathReport to HSEWithout delay; report received within 10 days
A specified injury to a worker (list below)Report to HSE (online, or phone 0345 300 9923 for fatal and specified injuries)Without delay; report received within 10 days
A worker off work or unable to do normal duties for more than 7 consecutive daysReport onlineWithin 15 days of the accident
A worker off for more than 3 days (but not more than 7)Record it, don't report itKeep the record at least 3 years
A member of the public taken straight from the scene to hospital for treatmentReport to HSEWithout delay; within 10 days

Count the 7 days without the day of the accident, but include weekends and rest days. A visit to hospital just for a check or an X-ray isn't "treatment".

The specified injuries:

  • Fractures, except fingers, thumbs and toes
  • Amputation of an arm, hand, finger, thumb, leg, foot or toe
  • Injury likely to cause permanent loss or reduction of sight
  • Crush injury to the head or torso damaging the brain or internal organs
  • Serious burns: over 10% of the body, or damaging eyes, breathing or vital organs
  • Scalping that needs hospital treatment
  • Loss of consciousness from a head injury or asphyxia
  • Enclosed-space injury causing hypothermia or heat illness, or needing resuscitation or 24+ hours in hospital

Who reports: employee vs self-employed sub

Injured person Who reports under RIDDOR Insurance to call
Your employeeYou, the employerYour employers' liability insurer
A self-employed sub working on your siteThe person in control of the premises (on most sites, the contractor running it). The sub should make sure you knowYour insurer, and ask for the sub's own insurance details
An agency workerCheck with the agency and take advice; record it either wayYour insurer and the agency
A member of the publicThe person in control of the work or premisesYour public liability insurer

Employers must hold employers' liability insurance of at least £5 million. If you're not properly insured you can be fined £2,500 for every day. Ring your insurer or broker today, follow the notification terms in your policy, and send them your records. To check who your policy covers before the next job, read employers' liability insurance for subcontractors.

Free 1-on-1 call

Not sure your safety paperwork would stand up after an accident?

Book a free call and we'll go through it with you.

4Step 4 of 5

What to tell the client, and what not to say

Call the client the same day, then confirm in writing. Keep to facts.

"There was an accident on site today. [A worker] was injured while [task] and has been [treated on site / taken to hospital]. The area is made safe and work there has stopped while we look at what happened. We've informed [our insurer / the HSE, if reportable]. Work elsewhere on site [continues / restarts on day]. I'll update you on [day]."

Do say Don't say
What happened, in facts Guesses about the cause
What you've done to make it safe "It was our fault" or "he was messing about"
Who you've informed Promises of money or compensation
When you'll update them Anything about the injured person's private medical details
5Step 5 of 5

Days 2 to 7: find the cause and fix it

  • Investigate: what was being done, how it was planned, what went wrong. Talk to the people involved.
  • Review the method statement and risk assessment for that task. Change them if they failed, and brief the team.
  • Keep the file: accident book entry, RIDDOR report reference, photos, witness statements, insurer correspondence. RIDDOR records must be kept for at least 3 years.
  • Expect questions. The HSE, your insurer and the client may all ask for your records. The better the file, the shorter the conversation.

Craftex holds CHAS, SafeContractor and ISO 9001, 14001 and 45001. Those schemes test exactly this: how you plan work, record incidents and learn from them. Our accreditation service sets up the same system for contractors, and the CHAS vs Constructionline vs SafeContractor comparison helps you pick a scheme. To get your own records checked, book a free strategy call.

Free 1-on-1 call

Want site safety records that win tenders as well as pass inspections?

Book a free strategy call.

Print this card for every site

This is general information from a contractor's experience, not legal advice. For your situation, speak to a health and safety adviser or a solicitor.

Checklist

Accident on site: the first 24 hours

  • First aid, 999 if in doubt, area made safe, work stopped there
  • Accident book filled in, photos taken, witnesses written down
  • RIDDOR test done: death or specified injury reported without delay; over-7-day within 15 days
  • Insurer told, following the policy's notification terms
  • Client called and updated in writing, facts only
FAQ

Frequently asked questions

What should I do after an accident on my building site?

Give first aid and call 999 if needed, make the area safe and stop work there, then record what happened: accident book, photos, witnesses. Check whether it's reportable under RIDDOR, tell your insurer, and update the client. This is general information from a contractor's experience, not legal advice. For your situation, speak to a health and safety adviser or solicitor.

Which injuries are RIDDOR reportable in construction?

Deaths, and specified injuries to workers: most fractures (not fingers, thumbs or toes), amputations, injuries likely to cause permanent loss of sight, serious crush injuries to the head or torso, serious burns, scalping needing hospital treatment, loss of consciousness from a head injury or asphyxia, and certain enclosed-space injuries. Also injuries that keep a worker off normal duties for more than 7 days, and members of the public taken straight to hospital for treatment.

A self-employed subcontractor was injured on my site. Who reports it?

For a specified injury or an over-7-day injury to a self-employed person working on premises someone else controls, the person in control of the premises reports it. On most building sites that's the contractor running the site. The sub should make sure you know.

Who is liable when a worker is injured on site in the UK?

It depends on the facts, the contracts and who controlled the work. Employers must hold employers' liability insurance of at least £5 million for their employees. Don't admit liability on the day: record the facts, tell your insurer and take advice.

Free strategy call

Run sites that pass any safety check

Book a free strategy call. We'll look at your health and safety set-up, accreditations and site records.

Takes 2 minutes to apply.