How to Create a Construction Programme, Step by Step

Sviat Jay
Sviat JayFounder of BizMentor & Craftex. Updated , 5 min read
Team going through drawings outdoors on site

The short answer

To create a construction programme, list every stage of the job, give each a realistic duration, link the stages that depend on each other, add material lead times and inspections, leave float before the finish date, then share it with the client and update it every week.

  1. A programme is a promise with dates. It tells the client, your site lead and every subbie what happens when.
  2. Seven steps: stages, durations, dependencies, lead times and inspections, float, baseline, weekly update.
  3. Start from the finish date and the long-lead items. A spreadsheet bar chart is enough for jobs under about £250K.
  4. Update it every Friday and send the client the changes with the reason.

Most small builders run jobs from a start date and a rough idea. The client asks "when will you finish?" and gets a guess. Then the windows are eight weeks out, the plasterer is booked elsewhere and the finish date slides one excuse at a time.

A construction programme fixes that. It is the schedule of the job: every stage, how long it takes, what depends on what and the key dates. Craftex writes a programme for every project it runs.

Here is how to create a construction programme in an afternoon, with a layout you can copy. Want us to look at how you plan your jobs? Book a free strategy call.

What a good construction programme does

  • For the client: shows when each stage happens and when they must make decisions (tiles, kitchen, sanitaryware).
  • For your site lead: shows what comes next and what must be ready for it.
  • For your subbies: gives them dates they can book you in for, weeks ahead.
  • For you: shows early when a job is slipping, while you can still act, and supports any claim for extra time.

If you run several jobs, the programme is the backbone of the routine in how to manage multiple building projects.

1Step 1 of 7

Step 1: List every stage of the job

Walk the job in order from site set-up to handover and write each stage as a line. Break big stages down until each line is something one trade or gang does. "First fix" becomes "first fix electrics" and "first fix plumbing".

Include the stages builders forget: skip and welfare set-up, client decisions, inspections, deliveries, drying times, cleaning, snagging and handover.

2Step 2 of 7

Step 2: Give each stage a realistic duration

Use your own past jobs, not hopes. Ask the subbie how long they need for this job, then check it against what happened last time. Count working days, and allow for drying and curing times (screed, plaster) that nobody can rush.

3Step 3 of 7

Step 3: Link the stages that depend on each other

Some stages cannot start until another finishes: no plastering before first fix, no kitchen fit before the floor. Note for every line which stage it waits for. The longest chain of dependent stages from start to finish is your critical path. Any delay on that chain delays the finish date. Stages off the critical path have some slack.

4Step 4 of 7

Step 4: Add lead times, inspections and client decisions

Work backwards from when each item is needed on site:

Item Put on the programme
Windows, doors, rooflights Order date = needed date minus supplier lead time
Steels and structural items Engineer's drawings, fabrication, delivery
Kitchen, bathroom ware, tiles Client decision deadline, order date, delivery
Building control inspections Each stage your building control body needs to see
Party wall, utilities, scaffold Notices and bookings before work starts

Long-lead items often decide the whole programme. Put them in the day the contract is signed, and give the client a written deadline for every decision.

Pencil resting on printed architectural drawings
Mistake to avoid

Letting the client choose tiles and the kitchen "later". Late decisions are the most common cause of delay on residential jobs, and without a written deadline the delay is yours.

5Step 5 of 7

Step 5: Leave float before the finish date

Do not promise the client the date your perfect programme gives you. Leave a buffer before the completion date for weather, late deliveries and the unknowns you find when you open up walls. Show the client the completion date, keep the float as your own.

Free 1-on-1 call

Want us to look at how you plan your jobs?

Book a free call and we'll go through a live programme with you.

6Step 6 of 7

Step 6: Draw it and save the baseline

A spreadsheet is enough for most jobs under about £250K. Use one row per stage and one column per working week (or day on short jobs):

Column What goes in it
Stage First fix electrics
Who Subbie or gang name
Waits for Studwork complete
Start Date
Duration Working days
Finish Date (formula)
Weeks across Shade the cells the stage runs in

Mark milestones (structure complete, watertight, plastered, handover) and the critical path in a different colour. Save a copy as the baseline: the programme the client signed up to. Every future version is compared with it.

7Step 7 of 7

Step 7: Update it every Friday

Each Friday, mark actual progress, move the stages that are affected and check the completion date. Send the client the updated programme with their Friday update: done this week, next week, decisions needed and any change in dates with the reason. A programme nobody updates is decoration.

Architect working on a drawing with pencil and ruler

Example: a single-storey rear extension

Example only. Your durations depend on the job, the team and the site.

Stage Example duration Waits for
Set-up, scaffold, welfare, skip 2 days Contract signed, notices served
Strip-out and excavation 4 days Set-up
Foundations and inspection 4 days Excavation
Drainage and inspection 3 days Foundations
Brickwork and blockwork to plate 10 days Foundations
Steels installed 2 days Engineer's drawings, delivery
Roof structure and covering 6 days Walls to plate, steels
Windows and doors 2 days Roof on, supplier lead time
First fix electrics and plumbing 5 days Watertight
Plastering and drying 8 days First fix
Floor screed and drying 3 days plus drying First fix
Kitchen fit 5 days Screed dry, client choices made
Second fix and decoration 8 days Plaster dry, kitchen in
Snagging, clean and handover 3 days All trades complete

Some of these run in parallel; the bar chart shows which.

Help putting it into practice

Programmes are one part of running jobs without you on site. Sviat Jay runs Craftex, a London design and build company, and mentors owners one-to-one himself. He starts where your business leaks most, whether that is planning, pricing or sales.

The flagship is one-to-one, by application; smaller firms start in small groups (max 10–20) with regular one-to-ones. Built for results in about 4 months, not 1–3 years. To start with your jobs, book a free strategy call.

Take the 4-minute Construction Business Scorecard to see which system to fix first. Need programmes produced for a tender? Our estimating and pre-construction service covers them.

Free 1-on-1 call

Ready to run jobs on a programme, not on hope?

Book your business assessment.

Checklist

Write your programme this week

  • List every stage of your next job, including inspections and decisions
  • Ask each subbie for their duration and check it against your last job
  • Put every long-lead item in with an order date
  • Leave float before the date you tell the client
  • Book Friday 30 minutes to update it
FAQ

Frequently asked questions

What is a construction programme?

A construction programme is the schedule of a building job: every stage, how long it takes, the order it happens in and the key dates. In the UK it is usually shown as a bar chart (Gantt chart) and shared with the client, the site team and subcontractors.

How do I make a construction programme in Excel?

List the stages down the first column, add start date, duration and the stage each one depends on, then shade one cell per working day or week across the sheet to make a bar chart. Mark lead-time orders, inspections and the completion date, and save a copy as the baseline.

What should a construction programme include?

Every stage of work, durations, dependencies between stages, material lead times and order dates, inspections and sign-offs, client decisions with deadlines, float, the completion date and the date of the last update.

How often should a construction programme be updated?

Weekly on most small and medium jobs. Update actual progress every Friday, move the affected stages, and send the client what changed and why.