JCT vs a Bespoke Building Contract for Private Clients

The short answer
A JCT form is balanced and well known. Your own contract can protect your payments, your design and your supply chain, as long as it stays fair to consumers. Sviat Jay advises his mentees to use their own with private clients.
- JCT is written to be fair to both sides. Your own contract can be written around how your business gets paid and protected.
- With homeowners, the Construction Act does not apply. Your right to suspend for non-payment and to adjudicate exists only if your contract gives it.
- Consumer law sets the limits. Unfair terms do not bind a consumer, and the main terms must be clear and prominent.
- Put your design and your people in the contract: design ownership until payment, and no hiring your team or subcontractors around you.
Bespoke building contract vs JCT: with private clients, the choice decides how you get paid and who can go around you. Here's the case for your own contract and the consumer-law limits. Want yours checked against how you actually work? Book a free strategy call.
Sviat's position in one paragraph
Sviat Jay runs Craftex, a London main contractor, and mentors construction business owners one-to-one. With private clients, he advises them to use their own contract instead of a JCT form. A standard form is written to be fair to both sides.
A contract written for your business can strengthen your position as the contractor. It covers how you get paid and what happens when the client changes their mind. It also covers who owns the design and who may hire your people.
He adds one rule for every job: sign non-solicitation and non-compete agreements with everyone involved. Architects, designers, consultants, subcontractors. Otherwise a subcontractor takes your client, or the client hires your subcontractor directly. Right now Sviat has two live cases of clients trying to go around him.
This page is general information, not legal advice. Have your contract drafted or reviewed by a construction solicitor.
JCT vs bespoke: honest pros and cons
| Option | Strengths | Weaknesses | Best for |
|---|---|---|---|
| JCT Home Owner (HO/B, HO/C) | Plain English, £40–£46 + VAT, recognised by homeowners and lenders, own adjudication rules | Balanced, not contractor-led; JCT text cannot be edited in JCT On Demand; nothing tailored to your payment stages or supply chain | Small domestic jobs where the client insists on a standard form |
| JCT Minor Works / Intermediate / Design and Build | Well tested, familiar to architects, required on many tenders | Clients' lawyers add schedules of amendments that shift risk to you; long for a private client to read | Commercial clients, architect-run jobs, tenders |
| Your own bespoke contract | Built around your payment stages, variation process, design ownership and non-solicitation; short enough for a client to actually read | Costs a solicitor's drafting fee; must pass consumer fairness rules; less familiar to lenders and architects | Private clients and design-and-build work you win directly |
Problems like this usually trace back to cash and contracts. Take the free 4-minute Construction Business Scorecard: 18 questions on your pipeline, sales, pricing, cash flow and systems, with your weakest area shown first. Want someone to run valuations, variations and final accounts for you? See our commercial management service.
Why homeowner work changes the picture
On commercial work, the Construction Act gives you payment rights whatever the contract says. You can suspend after at least seven days' notice for an unpaid sum, and you can adjudicate. "Pay when paid" clauses don't work.
None of that applies to a contract with a residential occupier: someone having work done on the home they live in.
So with a homeowner, your contract must give you a payment schedule and a right to pause when a stage goes unpaid. It must also give you a fast way to settle disputes. Otherwise you don't have them. That is the practical case for your own contract with private clients.

What a contractor-friendly contract should cover
These are the clauses that protect a contractor or design company on private work. Write them in plain words so the client actually reads them.
- Payment schedule and deposit. Stages tied to visible milestones, the amount at each stage and the due date. Clayton, a plasterer we worked with, now signs with £5K upfront and staged payments. Individual results, not typical or guaranteed.
- Variations procedure. No extra work without a written instruction and an agreed price or rate, sent before you start it.
- Suspension for non-payment. Your right to stop work, after written notice, when a stage payment is late, and to recover the cost of stopping and restarting.
- Design ownership. You keep ownership of your drawings and design; the client's right to use them starts when you are paid in full.
- Client-supplied items. Who orders, checks and stores them, and what happens to the programme and price when they arrive late or wrong.
- Delays caused by the client. Late decisions, late access, late payments: more time and the cost of the delay. A decision schedule makes this work in practice: see when a client keeps changing their mind.
- Non-solicitation of your team. The client may not hire your staff, subcontractors or designers directly for the job, or for a set period after it, without your agreement.
- Defects and handover. When the job counts as finished, how long you come back for defects, and how snags are reported. Your defects period isn't your only exposure: see how long a builder is liable for defects.
- Disputes. A route to settle disputes quickly, such as adjudication or mediation, before court.
These clauses earn their keep on the bad day. Here is what to do when a client wants to sack you mid-job.
Want your contract, payment stages and variation process built properly?
Book a free call. We'll show you how Craftex does it.
The consumer-law limits you can't write around
A contract with a homeowner is a consumer contract. Your own terms are allowed, but the Consumer Rights Act 2015 and the Consumer Contracts Regulations 2013 decide how far they can go.
- Unfair terms don't bind the client. A term is unfair if, contrary to good faith, it creates a significant imbalance against the consumer. The Act's grey list includes taking disproportionate sums on cancellation and changing the terms or price on your own. It also covers terms the client had no real chance to read.
- Price and scope must be clear and prominent. Only then are they protected from a fairness challenge.
- You can't exclude reasonable care and skill. A clause removing that duty does not bind a consumer.
- 14 days to cancel off-premises contracts. If you sign in the client's home, they normally have 14 days to cancel. To start inside that period you need their express request on a durable medium; an email will do. If you never gave the cancellation information, the client may owe nothing for work done in that period. What to do when it happens: client cancelled within 14 days.
The practical rule: write one-sided protections as reasonable, clearly explained procedures (notice, a cure period, a fair cost), not as penalties. A construction solicitor can tell you where the line sits for your contract.
Copying a commercial contractor's terms into a homeowner job. Clauses that work between businesses, like large cancellation charges, can be unfair against a consumer and simply fall away.
When a JCT form is still the right call
Use the JCT form when a commercial client, main contractor or lender requires it, when an architect runs the job, or when you are tendering. Then the work is in the details: price the risk in their schedule of amendments, and run notices, valuations and variations on time.
Want a contract set up for your private clients? Book a free strategy call. Our JCT hub and the forms comparison cover how to choose and what to check.
Whatever form you sign, add your own agreements with the people around the job. The non-compete and non-solicitation guide covers subcontractors, architects, designers and consultants.
Tired of clients and subcontractors setting the terms?
Book a free strategy call and get your contracts and processes right.
Before you send your next private-client contract
General information as of October 2026, not legal advice. Have your contract drafted or reviewed by a construction solicitor before you use it.
Private-client contract check
- Payment stages, deposit and due dates are written in plain words
- No extra work starts without a written, priced instruction
- You can pause work, after notice, when a stage is unpaid
- Design ownership passes only on full payment
- The client may not hire your team or subcontractors around you