Apply
For UK subcontractors & contractors

Payment Applications in Construction: Get Paid in Full

Sviat Jay
Sviat JayFounder of BizMentor & Craftex. Updated , 5 min read
Calculator and glasses on paperwork

The short answer

Submit on the exact date your contract says, value the work done to that date line by line, add materials, agreed variations and dayworks, deduct retention and what's already been paid, and attach the evidence. A clear application on time is the hardest one to cut.

  1. Dates first. Your contract sets the valuation date and the due date. Miss it and your payment slips a whole month.
  2. Value line by line, then add what's yours. Work against your contract sum analysis or schedule. Add agreed variations, signed dayworks and materials on site (if the contract allows).
  3. Deduct retention and previous payments, then attach the evidence: photos, signed dayworks, variation instructions, delivery notes.
  4. Know what comes back: a payment notice within 5 days of the due date, and any pay less notice before the deadline.

You did £38,000 of work last month. The main contractor paid £24,000. When you ask why, the QS says your application "didn't have the backup" or came in "after the valuation date". Now the difference rolls into next month, and maybe the one after.

Most cash lost on commercial jobs isn't stolen. It's lost in the application: late, vague, or missing the paperwork that makes it hard to cut. Here's how to write a payment application in construction that gets paid. To check your applications with our team, book a free strategy call.

This is general information on the rules in England and Wales as of October 2026, not legal advice.

1Step 1 of 5

Check your payment terms before the first application

Read the payment clause before you start work, not when the first payment is short. You're looking for five things:

Term What to look for
Valuation or application date The day each month your application must arrive
Due date When the payment becomes due, usually tied to the valuation date or your application
Final date for payment The last day they can pay. It must be a fixed period after the due date
Notice periods When their payment notice and any pay less notice must arrive
Retention The percentage held back, and when each half is released

Watch for clauses that don't hold up. "Pay when paid" (you get paid when the main contractor does) is ineffective under the Construction Act unless the party above is insolvent.

In 2026 the Technology and Construction Court looked at a clause that pushed the final date back by however many days an invoice was late. It held the clause didn't comply. So the statutory Scheme's 17-day period applied instead of the contract's 30 days.

If your contract has no compliant payment terms, the Scheme fills the gap. Payment is due 7 days after the end of each 28-day period (or when you claim, if later). The final date for payment is 17 days after the due date.

Canary Wharf towers across the dock
Mistake to avoid

Signing a subcontract with 60- or 90-day payment terms because "that's what they all are". Negotiate before you sign. After, you're financing their project.

2Step 2 of 5

What goes in the application

Make the payer's QS's job easy. Every application should show, in this order:

  • Header: project, contract or order number, application number, valuation date.
  • Contract works: each line of your contract sum analysis or schedule, with the value complete to date (percentage or measured quantity).
  • Variations: agreed ones at the agreed price; pending ones listed separately with your price.
  • Dayworks: signed sheets, priced at the agreed rates.
  • Materials on site: if your contract allows payment for them, with delivery notes.
  • Gross valuation: the total of all of the above to date.
  • Less retention at the contract rate.
  • Less previous payments (certified or paid to date).
  • Amount now due, excluding VAT, with the VAT treatment shown (most subcontract work between VAT-registered businesses falls under the domestic reverse charge).
Calculator on handwritten figures
An application the QS can check in ten minutes gets paid. One they have to work out for themselves gets cut.
Free 1-on-1 call

Still getting less than you applied for?

Book a free call with our team. We check your applications and payment terms, and where your cash is held back.

3Step 3 of 5

An example application

Here's an illustrative example for a £180,000 drylining subcontract, application no. 4:

Line Contract value Complete Value to date
Metal stud partitions £72,000 85% £61,200
MF ceilings £48,000 60% £28,800
Boarding and taping £45,000 40% £18,000
Preliminaries £15,000 50% £7,500
Contract works to date £115,500
Agreed variations V01–V04 £8,400
Signed dayworks DW01–DW06 £2,150
Gross valuation £126,050
Less retention at 5% −£6,302.50
Less previous payments (apps 1–3) −£84,000
Amount now due (ex VAT) £35,747.50

Notice the prelims line. Preliminaries (site management, welfare, access, small plant) are time-related, so claim them as time passes, not only when the work finishes.

Free 1-on-1 call

Applications going in but less coming back?

Book a free call and we'll go through your last three with you.

4Step 4 of 5

Attach the evidence

The QS can only pay what they can check. Attach:

Restaurant with brick walls, deli counter and hanging plants
  • Dated photos of each area claimed, ideally with a marked-up drawing showing what's complete.
  • The written instruction or "agreed" email for every variation claimed.
  • Signed dayworks sheets for every daywork claimed.
  • Delivery notes for materials on site.
  • Your variation register, so the running total matches theirs.

Send it the way the contract says (often email to a named person) and keep proof of the date and time it went.

5Step 5 of 5

What should come back, and when

Once your application is in, the clock runs. Under the Construction Act:

What When If it doesn't happen
Payer's payment notice Within 5 days of the due date Your application (or a notice in default) can become the sum due
Pay less notice (if they want to pay less) Before the contract deadline; under the Scheme, at least 7 days before the final date Late or empty: the notified sum must be paid
Payment By the final date for payment Statutory interest, a 7-day suspension notice, adjudication

Put these dates in your calendar on the day you submit. If a pay less notice arrives, follow our 7-day plan for a pay less notice. If the money doesn't arrive at all, see main contractor not paying, which covers interest, suspension and adjudication. For retention held back long after the job, see retention money not released.

From Sviat

The subcontractors who get paid in full aren't the ones who argue best. They're the ones whose application lands on the right day, with every line backed up, every month.

Homeowner jobs are different

The Construction Act excludes contracts with a homeowner for work on their own home. There, you only have the stage payments your contract sets out. See how much deposit to take and a stage payment schedule you can copy.

Salon reception desk with a staircase behind

Payment application checklist

If you'd rather a commercial team prepared and chased your applications every month, that's what our commercial management service does. It uses the system Craftex runs on its own projects.

To score your cash flow against the other five areas of your business, take the free 4-minute Construction Business Scorecard. Want to fix the business behind the paperwork? 1-to-1 mentoring with Sviat, who runs Craftex today, is built to show results in about 4 months rather than 1–3-year programs. To start, book a free strategy call.

Checklist

Before your next application goes in

  • You know the valuation date, due date and final date
  • Every line is valued against the contract sum analysis
  • Variations and dayworks are backed by signed paperwork
  • Retention and previous payments are deducted
  • Notice deadlines are in your calendar the day you submit
FAQ

Frequently asked questions

What is a payment application in construction?

A written claim, usually monthly, for the value of work done to a set date, plus agreed variations, dayworks and materials, less retention and previous payments. On most commercial contracts it starts the payment cycle: it fixes the due date, and the payer must respond with a payment notice or pay less notice within set periods.

What should a payment application include?

The project and contract reference, the valuation date, a line-by-line valuation of work done against the contract sum, agreed variations, signed dayworks, materials on site if the contract allows, the gross total, retention, previous payments and the amount now due. Attach photos and the paperwork behind each variation.

When should I submit a payment application?

On or just before the date your contract gives. If the contract has no compliant payment terms, the Scheme for Construction Contracts applies, with payment due 7 days after the end of each 28-day period or when you make your claim, whichever is later, and a final date for payment 17 days after that.

Do I have a right to interim payments?

On construction contracts covered by the Construction Act, yes, unless the work is to last less than 45 days. Contracts with a homeowner for work on their own home are excluded, so there your stage payments come only from what the contract says.

What if I don't get a payment notice?

If the payer doesn't send a payment notice within 5 days of the due date, your application usually stands as the notified sum, if the contract allows the application to act as your notice. Otherwise you can send a notice in default. The payer then has to pay that sum by the final date unless they serve a valid pay less notice.

Free strategy call

Get paid in full on every application

Book a free strategy call. We'll look at your applications, your payment terms and where your cash is being held back.

Takes 2 minutes to apply.