Pay Less Notice Received? What to Do in the Next 7 Days

Sviat Jay
Sviat JayFounder of BizMentor & Craftex. Updated , 6 min read
Tall building wrapped in scaffolding during construction

The short answer

Check the date first. A pay less notice must arrive before the deadline in your contract (under the statutory Scheme, at least 7 days before the final date for payment) and state the sum and how it was worked out. Late or empty, it's not valid and the notified sum is due.

  1. Check the date and the content. Under the Scheme, a pay less notice must be given at least 7 days before the final date for payment, and state the sum and how it was calculated.
  2. Late or missing = the notified sum is due. Without a valid pay less notice, the payer must pay the sum in the payment notice, or your application if they sent no payment notice.
  3. Valid but wrong? They pay the lower sum on time; you challenge the valuation with backup, in your next application or through adjudication.
  4. Two levers if it isn't paid: suspension after 7 days' written notice, and adjudication, with a decision in 28 days from referral.

A pay less notice lands in your inbox two days before payday. The number is half what you applied for, and there's a line saying "valued as per site measure". Cash for wages is now short.

We sit on the other side of this. Craftex runs subcontract packages as a main contractor, so our commercial team values subcontractor applications and answers them with notices. Here is what we would check if one of ours landed on your desk. To go through your notice with our team, book a free strategy call.

This is general information from a contractor's experience, not legal or financial advice. For your situation, speak to a construction solicitor or a quantity surveyor.

1Step 1 of 5

The first 24 hours: 5 checks on the notice

Don't reply yet. Get your contract, your application and the notice side by side, and check these five things.

Check What to look for If it fails
1. On time? Arrived before the deadline in your contract. Under the Scheme: at least 7 days before the final date for payment Not a valid pay less notice: the notified sum is due
2. Sum stated? The amount they say is due (it can be zero) Not a valid pay less notice
3. Basis given? How the sum was calculated: measures, rates, deductions Weak notice: ask for the workings in writing
4. Right sender? From the person or role the contract names, to the address the contract names Note it, take advice before relying on it
5. Which payment? Clearly tied to your application number and payment cycle Ask which application it answers

These rules come from the Construction Act. They apply to construction contracts with businesses, not to a contract with a homeowner for work on the home they live in.

2Step 2 of 5

Pay less notice received: work out your dates

Most disputes about notices are really disputes about dates. Your contract sets them. If it doesn't, the statutory Scheme fills the gap.

Date Under the Scheme (if your contract is silent)
Valuation period 28 days by default
Payment due date 7 days after the end of the period, or when you apply, whichever is later
Payment notice deadline No later than 5 days after the due date
Final date for payment 17 days after the due date
Pay less notice deadline At least 7 days before the final date for payment

JCT and NEC subcontracts set their own periods. Use the ones in your contract; the Scheme is only the fall-back. If your subcontract says you're paid only once the main contractor is paid, that pay when paid clause usually doesn't hold.

Papers and a pen on a wooden table
Put the four dates on one page: application, due date, payment notice deadline and final date for payment.
From Sviat

Problems like this usually trace back to cash and contracts. Take the free 4-minute Construction Business Scorecard: 18 questions on your pipeline, sales, pricing, cash flow and systems, with your weakest area shown first.

3Step 3 of 5

If the notice is late, missing or empty

The law is simple here. To pay less than the notified sum, the payer needs a valid pay less notice, on time, stating the sum and the basis.

  • No payment notice either? On a Construction Act contract you can send your own notice of the sum due. Where the contract treats your application as the payment notice, your application sum is the notified sum.
  • Late pay less notice? It doesn't count. The notified sum must be paid by the final date.
  • A number with no workings? Ask for the calculation in writing the same day.

Send a short, dated letter. Don't argue the valuation yet. Just put the dates on record.

Subject: Application [no.] — [project] — notice received [date]

We received your notice dated [date] on [date] in respect of our application [no.] for £[x]. Under the subcontract the final date for payment is [date], so a notice of intention to pay less had to be given by [date]. Your notice was received after that date [or: does not state the basis on which the sum was calculated]. We therefore consider the notified sum of £[x] payable by [final date]. Please confirm payment. We reserve our rights, including to suspend performance and to refer the matter to adjudication.

Mistake to avoid

Replying with an angry phone call and nothing in writing. If this goes to an adjudicator, only dated documents count.

Free 1-on-1 call

Got a pay less notice this week?

Book a free call and we'll look at the dates and paperwork with you.

4Step 4 of 5

If the notice is valid but the valuation is wrong

A valid notice means the payer pays the lower sum on time. You don't get the full application just because you disagree. Your job now is to prove the value.

Calculator next to a laptop on a desk
Answer a cut with measures, not opinions: quantities, rates, photos and signed instructions.
  • Ask for their measure, line by line, and compare it with yours. If the cut is a list of back charges, use our contra charges plan.
  • Send your backup: marked-up drawings, dated photos, delivery notes, signed variation instructions.
  • Meet on site with the QS or package manager and walk the disputed areas.
  • Carry the difference into your next application with the backup attached.
  • Adjudicate if a large sum stays stuck. You can refer a dispute at any time. The adjudicator decides within 28 days of referral (extendable by up to 14 days with your consent). Check what adjudication costs first.
5Step 5 of 5

If the money still doesn't arrive

Whatever the sum due is, valid notice or not, it has to be paid by the final date. If it isn't, you have two statutory levers.

Lever What it does How Watch out
SuspensionStops some or all of your work until paid in fullAt least 7 days' written notice, stating the groundsGet the notice right; you're entitled to reasonable costs of suspending and the time back
AdjudicationA binding decision on what's dueNotice of adjudication, referral within 7 days, decision in 28 daysCosts money and time; worth it for sums that matter
Statutory interestInterest on late payment between businessesBase rate + 8%, plus £40–£100 per invoiceYour contract may set a different rate

Make your next application hard to cut

You can't stop every pay less notice. You can make yours rare and small. Our guide shows how to write a payment application, step by step, with an example.

This is how the commercial side works on Craftex projects, and what our commercial management service runs for contractors. To fix your applications and payment terms, book a free strategy call.

  • On the right day, to the right person, in the form the contract asks for. Diarise every date for the whole job.
  • Measured backup with every application: quantities, marked drawings, dated photos.
  • Variations signed before you do them, then priced in the next application.
  • One running account per package, so every application builds on the last.

Joe Crawford, Craftex's Commercial Director, has 37+ years in commercial construction. "Firm with clients, fair with subcontractors" is how we put it on our services page, and it starts with paperwork both sides can check.

Cover of The Cash Flow & Margin Blueprint
Free guide, 15 pages

The Cash Flow & Margin Blueprint

Payment terms, the UK rules that hit your cash, and a fill-in payment schedule.

Get the free guide
Free 1-on-1 call

Want applications that get paid in full, every month?

Book a free strategy call.

Before your next application goes in

This is general information on the rules in England and Wales as of October 2026, not legal advice. For a large or disputed sum, speak to a construction solicitor.

Checklist

Before you go

  • Every payment date for the job is in your diary
  • Each application has measures, photos and signed variations attached
  • You check every notice for date, sum and basis the day it arrives
  • You reply in writing and keep the dates on record
  • You know when to suspend and when to adjudicate
FAQ

Frequently asked questions

What is the difference between a payment notice and a pay less notice?

A payment notice says what the payer considers due on a payment date, and how it was worked out. It must be sent no later than 5 days after the due date. A pay less notice says they intend to pay less than the notified sum. It must state the sum they consider due and the basis, and arrive before the deadline: under the Scheme, at least 7 days before the final date for payment.

What happens if a pay less notice is issued late?

A pay less notice given after the deadline in the contract (or, under the Scheme, later than 7 days before the final date for payment) is not valid. The payer must then pay the notified sum by the final date. Write to them and say so, and keep the dates.

What happens if no payment notice is issued?

On a contract covered by the Construction Act, you can send your own notice of the sum you consider due. If your contract treats your application as the payment notice, that sum becomes the notified sum. Without a valid pay less notice, the payer must pay it.

The main contractor changed my application for payment. Is that allowed?

They can value your work lower, but to pay less than the notified sum they need a valid payment notice or pay less notice on time, stating the sum and how it was calculated. If they just pay less with no valid notice, write to them, ask for the balance and consider suspension or adjudication.

Can I stop work if a pay less notice cuts my payment?

If the sum due is not paid by the final date, you can suspend some or all of your work after giving at least 7 days' written notice stating the grounds. If the pay less notice is valid, the sum due is the lower figure: if that is paid on time, suspension is not available; challenge the valuation instead.