Final Account in Construction: How to Agree It and Get Paid

Sviat Jay
Sviat JayFounder of BizMentor & Craftex. Updated , 5 min read
Empty steel-portal warehouse unit with roller doors

The short answer

The final account is the contract sum adjusted for everything that changed, less valid contra-charges and payments made. Build it as the job runs, submit soon after completion, and watch the contract deadlines.

  1. Start it on day one. A final account built from a live variation register takes days. One rebuilt from memory takes months and loses money.
  2. Contract sum, then adjust, then submit early. Add variations and dayworks, adjust provisional sums, deduct valid contra-charges, and send the draft within weeks of practical completion.
  3. Deadlines matter. Under JCT SBC, a final certificate becomes conclusive unless proceedings start within 28 days; a letter disputing it isn't enough.
  4. Challenge contra-charges and agree in writing. Ask for evidence before any deduction, then record the retention release dates and chase them.

The job finished in March. It's now September and the final account still isn't agreed. The main contractor's QS has your variations "under review". There's a £9,000 contra-charge you've never seen evidence for, and your retention is stuck behind all of it.

For a lot of contractors, the final account in construction is where the margin they priced quietly disappears. Not in one big argument, but in months of delay and small deductions nobody has time to fight.

Here's how to build it, submit it and close it. If you have accounts stuck right now, book a free strategy call and we'll look at what's recoverable. This is general information from a contractor's experience, not legal advice.

1Step 1 of 5

What goes into a final account

A final account starts with the contract sum and adjusts it for everything that changed. Here's an illustrative example for a £240,000 fit-out:

Line Amount
Original contract sum £240,000
Less provisional sums omitted −£12,000
Add provisional sums as spent +£9,400
Add agreed variations (V01–V27) +£31,650
Add signed dayworks +£4,200
Add loss and expense (agreed delay) +£6,800
Adjusted contract sum £280,050
Less contra-charges (agreed) −£1,250
Final account total £278,800
Less paid to date −£255,000
Balance due (incl. retention still held) £23,800

Your contract decides which lines apply. Fluctuations, for example, only appear if the contract allows price adjustment.

Restaurant strip-out with old timber and equipment
Mistake to avoid

Leaving pending variations off the final account because "they never agreed them". If you were instructed and did the work, it goes in, with your evidence.

2Step 2 of 5

Build it while the job runs

A good final account isn't written at the end. It's the last version of three records you keep from day one:

Add a delay log too: dates you were held up, by whom, and what it cost. Loss and expense claims without contemporaneous records rarely succeed.

Two people in a meeting with laptops and sticky notes
The final account is just the last version of records you keep every month: variation register, dayworks, applications.
Free 1-on-1 call

Still waiting on a final account?

Book a free call with our team. We'll look at your open accounts, your variation records and what's realistically recoverable.

3Step 3 of 5

Know your deadlines

Final account deadlines differ by contract, and some are strict. Common ones:

Contract What the contract sets
JCT Minor Works 2016 Your final account documents within 3 months of practical completion (unless the contract particulars say otherwise); final certificate within 28 days of receiving them
JCT Standard Building Contract Final certificate no later than 2 months after the latest relevant event, such as the end of the rectification period; it becomes conclusive unless proceedings start within 28 days of the final payment due date
NEC4 ECC Project Manager assesses the final amount within 4 weeks of the Defects Certificate; disputes must be notified and referred within short time limits
Bespoke and amended contracts Often shorter time bars. Read the amendments

Under the JCT Standard Building Contract, a letter saying you disagree is not enough to stop the final certificate becoming conclusive. You need to start adjudication, arbitration or court proceedings in time. If a final certificate arrives that you don't accept, speak to a construction solicitor the same week.

Free 1-on-1 call

Final accounts open for months?

Book a free call and we'll look at what's recoverable and how to close them.

4Step 4 of 5

Submit, then negotiate

Send your final account as soon as practical completion is reached and the last variations are priced. Weeks, not months.

Salon treatment room with purple textured walls and velvet chairs
  • One summary sheet like the example above, then a schedule for each line.
  • Every variation with its instruction or "agreed" email, price build-up and photos.
  • Signed dayworks sheets, and the delay log behind any loss and expense.
  • A date by which you'd like to meet and agree it, and a request for the undisputed balance now.

In the meeting, agree the easy items first and write them down. Park disputed items in a list with each side's figure. A final account with 20 agreed items and 3 disputed ones is far easier to close than one big number nobody accepts.

From Sviat

Ask for the undisputed balance to be paid while you argue about the rest. Many payers will pay what nobody disputes; they just won't offer.

5Step 5 of 5

Contra-charges: don't just accept them

Contra-charges (back-charges) are deductions a main contractor makes for costs it says you caused: cleaning, damage, delay, remedial work, attendance. Some are fair. Many arrive at the end with no warning and no evidence.

Before you accept one, ask in writing for:

  • The contract clause that allows it.
  • When you were notified at the time, and given the chance to put it right.
  • The actual cost, with invoices or timesheets, not a round number.

If you can't get all three, say so in writing and keep it on the disputed list. Then check your retention position: once the account is agreed, put the release dates in the calendar. See retention money not released if they pass.

Homeowner jobs

On a homeowner job the "final account" is usually the last invoice plus extras. The same rules apply in a simpler form: itemise it, attach the agreed variations, and ask for the undisputed part first. See client won't pay the final invoice, and if it comes to it, our letter before action template.

Shop fitting room with timber panelling and a curtain

Final account checklist

If your final accounts keep dragging, our commercial management service prepares and negotiates them. It also reviews old ones and tells you what's realistically recoverable before you commit. To score how well your business protects its margin, take the free 4-minute Construction Business Scorecard.

Want the business itself to run tighter? 1-to-1 mentoring with Sviat, who runs Craftex today, can help. BizMentor mentoring aims for results in about 4 months rather than 1–3-year programs. Book a free strategy call to talk it through.

Checklist

Before you close your next job

  • Variation register, dayworks and delay log are up to date
  • Final account sent within weeks of practical completion
  • Every line has its paperwork attached
  • Contra-charges challenged unless clause, notice and cost are shown
  • Final certificate deadlines and retention dates are in the calendar
FAQ

Frequently asked questions

What is a final account in construction?

The final statement of what the contractor is owed for the whole job: the original contract sum adjusted for variations, dayworks, provisional sums, fluctuations and any loss and expense, less valid contra-charges and everything already paid. Once agreed, it fixes the last payment and the retention still to be released.

How long does a contractor have to submit a final account?

It depends on the contract. JCT Minor Works asks for the contractor's final account documents within 3 months of practical completion unless the contract particulars say otherwise. Other JCT forms and NEC set their own periods. Submit as early as you can: accounts sent within weeks of completion are settled faster.

Can a final certificate be challenged?

Usually only within a short window. Under the JCT Standard Building Contract, the final certificate becomes conclusive unless adjudication, arbitration or court proceedings are started within 28 days of the due date for the final payment. A letter disputing the figures is not enough. Check your own contract and act before the deadline.

What are contra-charges?

Deductions the main contractor makes from a subcontractor's account for costs it says the subcontractor caused: cleaning, damage, delays, remedial work, attendance. A valid contra-charge normally needs a contractual basis, notice and evidence of the actual cost. Ask for all three in writing before you accept it.

My final account has been sitting for months. What can I do?

Send a complete final account with supporting documents and a request to agree it by a date. Ask for any undisputed balance to be paid now. On contracts under the Construction Act, use the payment provisions: apply for the sum, and if it isn't paid or properly notified, adjudication is available.