For drylining contractors

How to Price Dry Lining Jobs for Main Contractor Tenders

Sviat Jay
Sviat JayFounder of BizMentor & Craftex. Updated , 5 min read
Metal stud framing and plasterboard during an interior strip-out

The short answer

Price a drylining package system by system, not as one m² rate: each partition, lining and ceiling type gets its own build-up, and openings, heads, bulkheads and attendances are separate items. Then qualify the tender so the risks you did not price stay with the main contractor.

  1. One rate for 'partitions' is how packages lose money. A single-board stud wall and a double-board fire and acoustic wall are different products. Take off and price each system type.
  2. Specs are tested systems. Fire and acoustic partitions must be built as the manufacturer's tested system, so price the exact boards, studs, insulation and head detail on the drawings.
  3. Items are where margin hides. Formed openings, deflection heads, bulkheads, access panels, pattresses and fire-stopping are priced each or per metre.
  4. Qualify every tender. Write down the drawings and revision you priced, attendances you expect and what you excluded. It is your evidence when things change.

Most drylining firms that go broke were busy right up to the end. They won packages on a single m² rate and fitted the partitions. At the final account they found the fire walls, heads, bulkheads and three weeks of waiting were never in the price.

This guide shows how to price dry lining jobs for main contractors. It is for owners of drylining and partitions firms in the UK. Not sure your rates cover the package? Book a free strategy call and we'll check a tender with you.

For setting your margin floor and turning hours into an m² rate, see our plastering and drylining margin guide. This page is about the tender itself. For domestic skims and re-plasters, see how to price plastering jobs.

Why one m² rate loses money

A drylining package is not one product. On a typical commercial floor you might have:

  • Single-board stud partitions between offices
  • Double-board fire and acoustic partitions around stairs, risers and plant rooms
  • Wall linings on dabs or on a metal furring system
  • MF ceilings with bulkheads and access panels
  • Shaft walls, boxing and encasements around services and steel

Each has different materials, outputs and risk. Average them into one rate and you win the easy packages at a loss on the hard parts.

1Step 1 of 5

Take off by system type

Go through the drawings and the partition schedule and measure each system separately:

  1. m² for every partition, lining and ceiling type, by height band (high walls need access and are slower)
  2. Linear metres for deflection heads, bulkheads, edge trims and beads
  3. Each for formed openings, access panels, pattresses and service penetrations
  4. The drawing numbers and revisions you measured from, written on the take-off

Then build a rate for each system from materials per m² plus your own fixing and taping outputs. If you do not know your outputs, job-cost the next three packages and you will.

Room mid-build with new timber floor and stud walls
Every partition type on the drawings gets its own line in the take-off.
2Step 2 of 5

Price dry lining jobs by specification, not description

"Fire-rated partition" is not a price. The drawings or specification name a tested system: board type and layers, stud size and centres, insulation, head detail, junctions and fire-stopping.

Fire and acoustic partitions only perform as tested if they are built that way. That is why Building Regulations Parts B and E care about the system, not just the board. That means:

  • price the exact system on the drawings, not a cheaper look-alike
  • price the extra layers, fixings and sealant the system needs
  • check who does fire-stopping at heads and penetrations, and price it or exclude it in writing
  • allow time for inspection and photos where the client or main contractor asks for evidence of the installation
Mistake to avoid

Swapping in a different board or stud "that does the same job" to win the tender. If it is not the tested system, it may not comply, and the cost of ripping it out is yours.

3Step 3 of 5

Price the items and attendances

Worked example: office floor package (example figures)

Item Quantity Cost rate Cost £
Stud partition, 2 × 12.5 mm board, insulated 180 m² £40 7,200
MF ceiling with taping 60 m² £39 2,340
Formed door openings 8 nr £45 360
Deflection head 45 m £9 405
Direct cost 10,305
Tender price at a 25% floor (÷ 0.75) 13,740

Price only the m² and leave out the openings and the head, and you tender £12,720. That is £1,020 gone before the first board goes up.

Then check what the main contractor provides and what you do. Hoisting, storage, waste removal, welfare, power and lighting cost real money when they are yours. List them as attendances by others or price them.

Free 1-on-1 call

Want your drylining rates built per system from your own outputs?

Book a free strategy call.

4Step 4 of 5

Qualify the tender so changes get paid

A tender return is not just a number. Send a short qualifications list with every price:

  • drawings and revisions priced, and the date of the tender
  • what is included and excluded, system by system
  • attendances you expect from the main contractor
  • your programme assumptions: areas available in sequence, no out-of-sequence returns
  • payment terms and retention as you priced them

When the drawings change, the area is not ready or another trade damages your boards, your qualifications are the evidence for the variation. Price it, send it, and get it agreed before you do the work.

Cover of UK Plastering & Drylining Profitability Playbook
Free guide, 14 pages

UK Plastering & Drylining Profitability Playbook

Turn your hours into true m² rates and job-cost every drylining package.

Get the free guide
5Step 5 of 5

Protect the cash under the subcontract

The subcontract decides your cash flow as much as your price does:

  • Retention If 5% of a £13,740 package is held, £687 waits until practical completion and the rest until the end of the defects period
  • CIS The main contractor deducts 20% from your labour if you are registered, 30% if you are not, unless you have gross payment status
  • Payment dates Apply on the dates in the subcontract, with measured quantities and photos
  • Pay less notices Know what to do when one arrives; see pay less notice received

For a four-minute score of your pricing, cash, sales and systems, take the free Construction Business Scorecard.

OSB-lined room under construction in sunlight
A profitable package can still leave you short of cash if retention and late payments are not planned for.

Win more packages from main contractors

Main contractors buy drylining from firms they trust to turn up, keep to programme and not fight every invoice. To get on their list:

  1. Be ready Cards for your team, insurance, RAMS and two or three references from recent packages
  2. Ask the estimating team which projects are going to tender, and return complete, qualified prices on time
  3. Deliver one package well, then ask the site manager and QS for the next one

See how to get subcontract work from main contractors for the full approach.

What this looks like in practice. Oleg, a 19-year-old taper and jointer in London, earned about £100 a day on site. Two months later his own company made around £7K a month profit, with a team of 10+. Individual results, not typical or guaranteed.

Sviat Jay runs a working construction company, Craftex, and mentors owners one to one himself. Craftex works as a main contractor, so he knows what a main contractor wants to see from a subcontractor. Every owner is different. Working one to one, he builds on what you are already good at.

The aim is results in about 4 months rather than 1–3-year programs. To talk through your next tender, book a free strategy call.

If you would rather have your tenders priced for you, see our construction estimating services.

Free 1-on-1 call

Want to win bigger drylining packages without pricing them at a loss?

Book a free strategy call.

Before you return your next drylining tender

Regulatory and tax points are general information as of October 2026. Check the details with your system manufacturer, building control and accountant.

Checklist

Before you go

  • Every system type is measured and priced on its own rate
  • Openings, heads, bulkheads and panels are priced each or per metre
  • The exact tested system is priced, and fire-stopping is priced or excluded
  • Attendances and exclusions are listed in your qualifications
  • Retention, CIS and payment dates are in your cash plan
FAQ

Frequently asked questions

How do I price dry lining jobs?

Take off the drawings by system type (each partition, wall lining and ceiling build-up), cost each per m² from materials and your own fixing and taping outputs, add the items priced each or per metre (openings, heads, bulkheads, access panels), add attendances you must provide, then divide by (1 − your margin floor).

Should drylining be priced per m² or by day rate?

Measured work on drawings is priced per m² and per item, because that is how main contractors compare tenders and value your applications. Keep day rates for small domestic jobs and for dayworks on variations, agreed in writing.

How do I get dry lining work from main contractors?

Get on their supply chain list (cards, insurance, RAMS, references), ask their estimating team which projects are coming to tender, return complete priced and qualified tenders on time, and deliver one package well. Repeat work comes from the site manager and QS who trust you.

Why do fire-rated partitions cost more to price and build?

They must be built exactly as the manufacturer's tested system: specified boards, stud sizes, layers, insulation and head and junction details, plus fire-stopping. More materials, more labour and more care, and on some buildings evidence such as photos of the installation.

What should be excluded from a drylining tender?

Typically: anything not shown on the drawings and revision listed, fire-stopping by others unless priced, works above or below specified heights, out-of-sequence working, unsuitable substrates, and attendances such as hoisting, waste removal and storage unless you have priced them.