Apply
For roofing contractors

Roofing Business Profit Margins: 5 Steps to Keep More

Sviat Jay
Sviat JayFounder of BizMentor & Craftex. Updated , 5 min read
Grand white stucco building with roof scaffold and hoarding at street level, a Craftex refurbishment in progress

The short answer

Roofing margin is lost to things you can't see on the day you quote: rain, scaffold time and rotten timber under the covering. Price all three before you start.

  1. Weather is a cost. In our example one lost day for two roofers is £438. Unpriced, it takes the job from a 30% to a 26% margin.
  2. Scaffold has a clock. Price the hire period you need, and agree in the quote what each extra week costs and who pays.
  3. Hidden timber is a provisional sum. Rotten battens, rafters or decking are priced at an agreed rate per m², approved in writing once the covering is off.
  4. Job-cost pitched and flat roofs separately. In our example the re-roof lost 11 points of margin and the flat roof gained 3.

A roofing business profit margin in the UK is lost on the roof: rain days, extra scaffold weeks and rotten timber. This page shows how to price all three in. Want your numbers checked? Book a free strategy call.

Why roofing margins disappear

A roofer prices a job from the ground, sometimes from a drone photo. The real job is only visible once the old covering is off.

Most lost margin on roofs comes from four places:

  • Weather Days the crew can't work but still gets paid
  • Scaffold Hire that runs on after the planned finish
  • Hidden timber Rot under tiles, felt or decking
  • Waste Skips that turn out bigger than planned

Each one can be priced. Most roofers leave them out to look cheaper.

Pricing properly is easier when the diary is full: see how to get more roofing work and how to get commercial roofing contracts.

Vertical drone shot of flat roofs and the street, 3-4 Hobart Place SW1
Drone view of flat roofs on a London terrace before works, at a site Craftex surveyed. A roof survey shows the covering, not the timber underneath.
1Step 1 of 5

Price the weather into hours and programme

From Sviat

Weather days are real. Plan for them in your hours and your programme — don’t donate them to the client.

Worked example: pitched re-roof, two roofers (example figures)

Item £
Labour: 2 roofers × 5 days = 80 hours × £27.40 2,192
Tiles, membrane, battens, lead 3,200
Scaffold (subcontract) 1,400
Skips and waste 500
Direct cost 7,292
Price at 30% floor, no weather allowance 10,417
Weather allowance: 1 day × 2 roofers = 16 h 438
Price at 30% floor with allowance 11,043

If it rains for a day and you priced £10,417, your cost rises to £7,730 and gross margin drops to about 26%. Two wet days and you are close to working for free.

The £27.40 is the true cost of an employee on £18 an hour once NI, pension and holiday are counted.

Base the allowance on your own records: lost days per job, by month and by roof type.

From Sviat

Which number is costing you most? Take the free 4-minute Construction Business Scorecard: 18 questions on your pipeline, sales, pricing, cash flow and systems, with your weakest area shown first. Need prices built for you? See our estimating service.

2Step 2 of 5

Put a clock on the scaffold

Scaffold is often the biggest item you don't control. Treat it as a package with a start and finish date (and if you run your own scaffolding, see how scaffolding firms price hire weeks):

  • Price the hire period your programme needs, plus the weather allowance.
  • State in the quote what each extra week costs and when it becomes the client's cost.
  • Name the reasons that make it the client's cost: late decisions, other trades, access delays.
  • Get the scaffold struck as soon as you're done — every idle week is margin.

A scaffold that stays up because the client's other trades are late is a variation. Write it down the day it happens.

Scaffold and access tower on a London refurbishment site
Scaffold on a London refurbishment. Every week it stands past the programme costs money.
Free 1-on-1 call

Want your weather and scaffold allowances worked out from your own jobs?

Book a free call.

3Step 3 of 5

Turn hidden timber into provisional sums

You can't price what you can't see. You can price how you'll charge for it.

  • Put a provisional sum or a rate per m² for replacement decking, and per metre for battens or rafters, in the quote.
  • When the covering is off, photograph, measure and send the client the cost the same day.
  • Start the repair only after a written yes.

The same applies to extra lead, flashings or chimney work the client asks for on the day. It also covers skips that turn out bigger than planned. Put the procedure in your contract, not just the quote: see what a contractor-friendly contract for private clients covers.

Mistake to avoid

Replacing rotten rafters "because it has to be done" and raising it at the final invoice. Without a written approval, you are negotiating after the money is spent.

Cover of UK Roofing Profitability Playbook
Free guide, 14 pages

UK Roofing Profitability Playbook

Get the free guide
4Step 4 of 5

Check building regulations before you quote

Regulations change what a re-roof costs. Check them before you price, not after.

  • Approval. One council's guidance says re-roofing 50% or more of the roof area, or changing insulation or ventilation, generally needs building regulations approval. Rules and thresholds can vary, so confirm with your building control body.
  • Insulation. When a roof is re-decked and re-covered, the insulation must be upgraded. On flat roofs that is material and labour.
  • Self-certification. Members of the NFRC's Competent Roofer scheme can self-certify their own work. Others pay building control, and that fee belongs in the quote.
  • Work at height. The law requires measures to prevent falls. Edge protection, towers and safe access are part of the job's cost.

Installing roof insulation in homes is zero-rated for VAT until 31 March 2027, so show the VAT treatment on the quote.

Period building behind blue hoarding and a scaffold fan
A live Craftex site in London. Hoarding, scaffold and safe access are part of what the job costs.
5Step 5 of 5

Job-cost pitched and flat roofs separately

Job Type Price Quoted GP Actual GP
Example A Re-roof £8,571 30% 19%
Example B Flat roof £2,400 35% 38%

The re-roof lost 11 points — usually weather, extra timber or unpriced extras. The flat roof beat its target.

Track on every roof: budgeted vs actual hours by stage (strip, prepare, cover, make good). Add weather days lost, scaffold weeks and timber found, and whether it was approved. After ten roofs you'll know your real weather allowance and which roof types to push. Want help setting this up? Book a free strategy call.

Small repairs need a minimum charge. Access, travel and setting up take the same time whether the repair is one slipped tile or ten.

The UK Roofing Profitability Playbook guide cover

Get the free PDF guide

14 pages. Sent to your inbox in 2 minutes.

Free 1-on-1 call

Want to see which roof types make you money?

Book a free strategy call and bring your last three jobs.

Before you send your next roofing quote

Regulatory and tax points are general information as of October 2026. Check the details with your building control body and accountant.

Checklist

Before you go

  • Weather allowance is in the hours and the programme
  • Scaffold period and extra-week cost are written in the quote
  • Hidden timber has a provisional sum or rate per m²
  • Building regs approval or self-certification is checked and priced
  • Last three roofs were job-costed by stage
FAQ

Frequently asked questions

What is a good profit margin for a roofing company?

Base it on your own figures: overheads as a % of turnover plus the net profit you want. If overheads are 20% and you want 10%, every roof needs at least a 30% gross margin after weather, scaffold and waste are priced in.

How do roofers price for bad weather?

Add an allowance of lost days to the labour hours and to the programme, based on your own records for that time of year and roof type. Cost those hours at your true hourly rate, so the price still hits your margin floor if it rains.

How do you price rotten timber you can't see when quoting?

Use a provisional sum or an agreed rate per m² (or per metre of rafter) in the quote. Once the covering is off, photograph what you find, measure it, and get written approval before replacing it.

Does re-roofing need building regulations approval?

Often, for larger jobs. One council's guidance says re-roofing 50% or more of the roof, or changing insulation or ventilation, generally needs approval, and re-decked and re-covered roofs need an insulation upgrade. Members of the NFRC's Competent Roofer scheme can self-certify. Check with your building control body.

How do I work out a roofer day rate?

Take each roofer's true hourly cost (wages plus employer NI, pension and holiday, divided by chargeable hours), multiply by the hours in a working day, and divide by (1 − your margin floor). Price access, scaffold and materials on top.

Free strategy call

Price every roof for the rain, the scaffold and the timber

Book a free strategy call. We go through your last three roofs and show where the margin went.

Takes 2 minutes to apply.