How to Price Electrical Jobs: A Guide for UK Electrical Contractors

The short answer
Price an electrical job from the hours it really takes, including survey, testing, certificates and notification, costed at your true hourly rate, plus materials and travel, then divide by (1 − your margin floor). Use a per-point rate to check the price, never to make it.
- A socket rate is not a price. In our kitchen example the job works out at about £102 a point, against a typical £65 per socket, because of the new circuit, testing and notification.
- Hours × true hourly cost. Not the wage you pay: with NI, pension and holiday, our example rate is £27.40 an hour.
- Markup is not margin. A 20% markup on materials earns only 16.7% margin. To hold a 30% margin you need a 42.9% markup.
- Price the call-out from cost. Travel, the first hour and the admin come to about £95 minimum in our example, before you open a single back box.
Most electricians price the way they learned on site: so much a socket, so much a light, "about £400 a day". Then the kitchen needs its own circuit and the board has no spare ways. The fitter moves the island after first fix. Testing and the certificate take a whole afternoon you never charged for.
This guide shows how to price electrical jobs so every quote makes money. It is for owners of UK electrical businesses. Want your rates checked against a real job? Book a free strategy call.
For setting your margin floor and budgeting each type of work, see our electrical profit margin guide. This page is about pricing the job in front of you.
Why a rate per socket loses money
Homeowner cost guides are a useful market check. Checkatrade's 2026 guide puts a new socket at about £55–£75 (average £65). It puts an electrician at about £50–£55 an hour and a day at around £400–£500. But a "point" means very different work:
- A spur off an existing ring in an empty room: quick, low risk
- A point on a new circuit Cable run, new way in the board, notifiable
- Points in a lived-in house Lifting floors, chasing, making good, dust sheets
- Points in a bathroom or kitchen Special locations, RCD checks, more testing
- Commercial points Containment, drawings, O&M manuals, longer payment
Quote them all at one rate and you win the easy jobs and lose money on the hard ones.
Know your numbers before you price anything
You need two numbers from your own books:
- True hourly cost. Wages plus employer NI, pension, holiday, van, tools, test kit calibration and insurance, divided by the hours you can actually charge. In our example that is £27.40 an hour for an employee on £18.
- Margin floor. Your overheads as a % of turnover plus the net profit you want. With 20% overheads and 10% profit, nothing goes out below a 30% gross margin.
Every price on this page is cost ÷ (1 − margin floor). At 30%, that is cost ÷ 0.7. The margin guide shows how to work out both numbers.

Markup on materials: the maths most electricians get wrong
"I put 20% on materials" sounds safe. It is not 20% profit. Markup is added to cost; margin is the share of the price you keep:
| Markup on cost | Margin you keep |
|---|---|
| 20% | 16.7% |
| 25% | 20% |
| 42.9% | 30% |
| 53.8% | 35% |
To convert: markup = margin ÷ (1 − margin). If your floor is 30%, a 20% markup on materials pulls the whole job below it.
The simplest fix is not to mark up materials separately at all. Add labour, materials and travel at cost, then divide the total by 0.7. The client sees one clear price, and every part of the job carries your margin.
Letting the client buy the fittings "to save money" and keeping your labour price the same. Your labour now has to carry the whole margin, and you carry the risk if their fittings are wrong.
Survey and price every stage of the job
Never price a rewire or a kitchen from a photo. On the visit, check the board: age, spare ways and RCD protection. Check the earthing and bonding, cable routes, what is under the floors and who lives in the house.
Then price the hours stage by stage:

- survey, quote and design time
- first fix: routes, chasing, back boxes, cable runs
- second fix: accessories, fittings, connections at the board
- testing, inspection and the certificate
- notification and admin for notifiable work
New circuits, consumer unit replacements and work in rooms with a bath or shower are notifiable in England. A scheme-registered electrician self-certifies; anyone else notifies building control before starting. That is time and a scheme fee on every such job.
Testing, certificates and Part P notification take real time on every job. Price them as a line, not as a favour.
Not sure your hourly cost and margin floor are right?
Book a free strategy call and we will check them with you.
A worked example: a new kitchen circuit and 15 points
Kitchen in a lived-in house (example figures). 8 double sockets on a new circuit, a new cooker circuit, 6 downlights. The board has spare ways.
| Stage | Hours | Cost £ |
|---|---|---|
| Survey, design, quote | 1 | 27.40 |
| First fix | 11 | 301.40 |
| Second fix | 6 | 164.40 |
| Testing and certificate | 3 | 82.20 |
| Notification and admin | 1 | 27.40 |
| Labour at £27.40/h | 22 | 602.80 |
Then add what is not labour:
Direct cost: £1,072.80. At a 30% floor the price is £1,072.80 ÷ 0.7 = £1,533, quoted as £1,535. Add VAT if you are registered, and your scheme's notification fee as its own line. That is about £102 per point.
Now the check. At the £65 average socket rate you would quote £975. That is £97.80 less than it costs you, before a penny of overheads. The rate looked "market". The job was not a spur.

UK Electrical Profitability Playbook
Work out your true hourly cost and margin floor, then job-cost every rewire, board change and EICR.
Get the free guideCall-outs, day rates and fixed prices
Use each method where it fits, and build all three from the same hourly cost:

| Method | Use it for | How to set it |
|---|---|---|
| Fixed price per job | Homeowners, rewires, kitchens, boards | Stage hours × cost + materials, ÷ (1 − floor) |
| Minimum / call-out charge | Faults, small jobs, one socket | Travel + first hour + admin. Our example: about £95 |
| Day rate | Dayworks, unknown scope, labour for a builder | 8 h × £27.40 = £219, ÷ 0.7 = about £313 minimum |
The call-out in our example is 45 minutes there and back, an hour on the job and 15 minutes of admin. That is 2 hours × £27.40 = £54.80, plus £10 for the van: £64.80 cost and about £95 price.
Checkatrade's guide gives a London example of £100 for the first hour, so the market will pay it. Below that, every small job is a donation.
If the market pays £400–£500 a day and your floor is £313, the gap is your profit. If you cannot get your floor, the answer is different clients or lower costs, not a lower price.
Price for the client, not just the circuit
The same 15 points are a different job for different clients:
- Homeowner. Lived-in house, more making good, more questions. Take a deposit for materials and get paid on completion, the same day.
- Landlord or letting agent. Private landlords must have the installation checked at least every five years, so EICRs come in volume. Price by circuits and hours, and agree remedial work rates in writing before you test.
- Builder or main contractor. CIS takes 20% of your labour if you are registered, or 30% if not, unless you have gross payment status. The VAT domestic reverse charge may apply, and retention is often held. Build the wait into your price and your cash plan. See how to win commercial electrical contracts.
If you are close to £90,000 of taxable turnover in a 12-month period, you must register for VAT. Price with it in mind before you reach it.
For a four-minute score of your pricing, cash, sales and systems, take the free Construction Business Scorecard.
Write a quote that protects your margin
A quote is not a number on a WhatsApp message. Put in writing:
- Scope. Points, circuits and fittings by room, and who supplies the fittings
- Compliance. Testing, the certificate and notification, each as a line
- Exclusions. Making good, decorating, faults found on existing circuits
- Payment. Deposit, stages or completion, and the date it is due
- Changes. Layout locked at first fix; moves after that are priced and agreed in writing
When the kitchen fitter moves the island, price the change there and then. See how to get paid for variations for how to do it without an argument.
What this looks like in practice. Dima, an electrician in our mentorship, put pricing and job-costing in place. Within about four weeks he took on around 10 people and was earning around £7–8K a month. His story is on Sviat's Russian-language YouTube channel. Individual results, not typical or guaranteed.
The order he did it in is in our guide on how to grow an electrical business.
Sviat Jay runs a working construction company, Craftex, and mentors owners one to one himself. Every electrical business is different: one owner is strong on the tools, another on sales. Working one to one, he builds on what you are already good at.
He is aiming for results in about 4 months rather than 1–3-year programs. To price your next job with us, book a free strategy call.

Want your electrical prices built from your own numbers?
Book a free strategy call.
Before you send your next electrical quote
Tax and compliance points are general information as of October 2026. Check the details with your accountant and your competent person scheme.
Before you go
- You surveyed the board, earthing, routes and the house
- Hours are estimated stage by stage, testing and admin included
- Labour is costed at your true hourly cost, not the wage
- Materials and travel are in at cost, and the price is cost ÷ (1 − floor)
- Scope, exclusions, payment and the first-fix lock are in writing