How to Price Roofing Jobs: A Guide for UK Roofers

Sviat Jay
Sviat JayFounder of BizMentor & Craftex. Updated , 8 min read
Roofer working on a house roof

The short answer

Measure the true roof area (plan area × pitch factor), take off materials with waste, estimate the hours stage by stage at your true hourly cost, add access and skips, then divide by (1 − your margin floor). Use per m² rates only to check the number.

  1. A per m² rate is not a price. On our 20 m² flat roof, a cost guide's £80 per m² comes to £1,600: about £78 below what the job costs to do.
  2. Measure the slope, not the plan. A 35° roof has about 22% more area than the footprint it covers, before waste.
  3. Hours × true hourly cost. An employee on £18 an hour costs about £27.40 per hour you can charge, before rain days and profit.
  4. Price what you can't see as a rate. Rotten decking, battens and lead are written as a rate per m² or metre, agreed before you fix them.

Most roofers price the way they were shown. A rate per m² for the covering, "about £300 a day", or what the last roof came to. Then the decking is soft, the skip fills by lunchtime, and the tower has to come back for a second day.

This guide shows how to price roofing jobs so every quote makes money. It is for owners of UK roofing businesses. Want your rates checked against a real roof? Book a free strategy call.

For setting your margin floor, weather allowance and scaffold terms, see our roofing margin guide. This page is about pricing the roof in front of you.

Why a rate per m² loses money on roofing jobs

Cost guides are a good market check. One 2026 guide puts an EPDM flat roof at £55 to £95 per m². A concrete tile re-roof comes in at £75 to £130 per m², scaffold included. But those are averages across very different roofs:

  • Small repair: slipped tiles, a leak, a flashing. Short on the roof, long on access and travel
  • Flat roof replacement: a garage, a dormer, an extension. Small area, the same skip and set-up
  • Ridge, hip and verge work: priced by the metre, slow on a steep pitch
  • Pitched re-roof: big area, scaffold weeks, timber you can't see
  • Chimney and lead: detail work, slow, and often the reason for the leak

Price all of them at one rate per m² and the small roofs lose money, because set-up, access and waste don't shrink with the area.

1Step 1 of 5

Know your numbers before you price anything

You need two numbers from your own books:

  1. True hourly cost. Wages plus employer NI, pension, holiday, van, tools and insurance, divided by the hours you can actually charge. Our playbook works on £27.40 an hour for an employee on £18.
  2. Margin floor. Your overheads as a % of turnover plus the net profit you want. With 20% overheads and 10% profit, nothing goes out below a 30% gross margin.

Every price on this page is cost ÷ (1 − margin floor). At 30%, that is cost ÷ 0.7, so one roofer-hour at £27.40 sells for about £39 before materials. The margin guide shows how to work out both numbers and how to price rain days in.

2Step 2 of 5

Measure the real roof, then take off materials

A pitched roof is bigger than the plan it covers. Measure the plan area, including the overhangs, and multiply by the pitch factor:

Roof pitch Multiply plan area by
30° 1.15
35° 1.22
40° 1.31
45° 1.41

A house roof covering 63 m² on plan at 35° is about 77 m² of slope. Price it at 63 m² and you are 14 m² short on tiles, membrane, battens and hours.

Then add waste. A common allowance is 10 to 15% for breakage and cuts, and around 20% for natural slate. Hips, valleys and dormers mean more cuts, so use the top of the range. Ridges, hips, verges and valleys are measured by the metre, not the m².

Close-up of grey interlocking concrete roof tiles
Tiles, battens and membrane are ordered for the slope area, not the footprint.
3Step 3 of 5

Survey before you price the hours

Never price more than a small repair from a drone photo. On the visit, check:

  • the covering, its age and the batten gauge, and whether you can match it
  • the timber: soft decking, sagging rafters, signs of an old leak inside the loft
  • the details: lead, chimneys, valleys, abutments and rooflights
  • access: scaffold or tower, parking, neighbours, where the skip goes
  • building regulations: how much of the roof you replace and the insulation

Write what you found on the quote. Anything you couldn't see goes in as a rate, for example £45 per m² of decking replaced (example rate). Agree it in writing before you fix it.

Re-roofing a large part of a roof, or changing its insulation, can need building regulations approval. Members of the NFRC's CompetentRoofer scheme can self-certify; otherwise the fee belongs in the quote. Edge protection, towers and safe access are part of the price, because the law requires measures to prevent falls.

Free 1-on-1 call

Not sure your hourly cost and outputs are right?

Book a free strategy call and we will check them with you.

4Step 4 of 5

A worked example: a 20 m² flat roof

Single-storey rear extension, 20 m², old felt stripped and replaced with EPDM (example figures). Deck sound, two roofers, a tower for access.

Task Hours Cost £
Set-up, tower and protection 3 82.20
Strip old felt, waste to the skip 5 137.00
Check and prepare the deck 3 82.20
Lay and bond the EPDM 6 164.40
Trims, upstands and outlet 5 137.00
Clean-up and handover 2 54.80
Labour at £27.40/h 24 657.60

Then add what is not labour:

Roofer's hands fixing a metal edge trim on a roof
Trims, upstands and the outlet take more hours than the membrane itself.
£600membrane, adhesive, trims and outlet
£250skip
£170tower hire, travel and parking

Direct cost: £1,677.60. At a 30% floor the price is £1,677.60 ÷ 0.7 = £2,397, quoted as £2,400 (plus VAT if you are registered). That is £120 per m².

Now the check. The cost guide's £80 per m² comes to £1,600: about £78 less than the job costs you to do, before a penny of overheads. Three roofer-days at £300 plus materials, skip and access at cost is £1,920, a 12.6% margin. The rate looked "market". The roof wasn't.

Mistake to avoid

Quoting a small flat roof at the per m² rate you use on big ones. A 20 m² roof needs the same skip, tower and set-up as a 60 m² one.

Day rate, per m² or fixed price: when each works

Use each method where it fits, and build all three from the same hourly cost:

Method Use it for Watch out for
Fixed price per roofHomeowners, re-roofs, flat roofs, chimneysWrite inclusions, exclusions and a decking rate, or extras become free
Minimum charge plus hourlyLeaks, slipped tiles, small repairsSet a minimum that covers access and travel
Day rate or per m² scheduleBuilders and main contractors, repeat workAgree it in writing; skips, access and rain days on top

Homeowners compare totals, so give them one clear price. Builders compare rates, so give them a schedule. Either way, the number underneath is hours × true hourly cost ÷ (1 − margin floor).

From Sviat

Weather days are real. Plan for them in your hours and your programme — don't donate them to the client.

Cover of UK Roofing Profitability Playbook
Free guide, 14 pages

UK Roofing Profitability Playbook

True hourly cost, weather allowances, scaffold time, provisional sums and job costing for roofing, with worked examples.

Get the free guide
5Step 5 of 5

Price for the client, not just the roof

The same roof is different work for different clients:

  • Homeowner. Lived-in house, neighbours, more questions. Take a deposit for the materials and get paid on completion, the same day.
  • Landlord or managing agent. Tenants to arrange, repeat repairs, slow approvals. Charge for a wasted visit and agree who pays the invoice.
  • Builder or main contractor. Roofing as one package on a bigger job, waiting on other trades. CIS takes 20% of your labour if you are registered (30% if not, unless you have gross payment status), and retention is often held. Build the wait into your price and your cash plan.

Say which VAT rate applies on every quote. Installing roof insulation in a home can be zero-rated until 31 March 2027; the roof covering itself is standard-rated. If you are close to £90,000 of taxable turnover in a 12-month period, you must register for VAT. Price with it in mind before you reach it.

For a four-minute score of your pricing, cash, sales and systems, take the free Construction Business Scorecard.

Old natural slate roof with uneven slates
An old slate roof hides its problems until the first row comes off.

Write a quote that protects your margin

A roofing quote is not a number on a WhatsApp message. Put in writing:

  • Area and covering. The m² you measured, the covering, the membrane and battens
  • What you found. Timber, details, anything that could change once the old covering is off
  • Access and waste. Scaffold or tower, how long it is hired for, and the skips
  • Rates for the hidden. Decking per m², battens and rafters per metre, lead per metre
  • Payment and extras. Deposit, the date payment is due, and extras priced in writing before you do them

When the client asks you to "just do the chimney while you're up there", price it there and then. See how to get paid for variations for how to do it without an argument.

When to walk away from a roofing job

Some roofs cost you money however well you fix them:

  • the client wants your price to match "a man who does it for less"
  • there is no time to get up and look, but they want a fixed price today
  • they won't agree a rate for the timber you can't see
  • the payment terms are 60 days on a job you can only fund for 30

Saying no to a bad roof keeps a day free for a good one. A full diary at a loss is still a loss.

What fixing prices first does. Dima, an electrician, started with his pricing and job costing. He then hired about 10 people in about 4 weeks and earned around £7,000 to £8,000 a month. It is a different trade, but the order is the same for a roofer. Individual results, not typical or guaranteed.

Sviat Jay runs a working construction company, Craftex, and mentors owners one to one himself. Every roofing business is different: one owner is strong on the roof, another on sales. Working one to one, he builds on what you are already good at.

He is aiming for results in about 4 months rather than 1–3-year programs. To price your next roof with us, book a free strategy call. If you'd rather hand the pricing over, our construction estimating service builds the quotes for you.

Free 1-on-1 call

Want your roofing prices built from your own numbers?

Book a free strategy call.

Before you send your next roofing quote

Regulatory and tax points are general information as of October 2026. Check the details with your building control body and accountant.

Checklist

Before you go

  • You measured the slope area, not the plan, and added waste
  • Hours are estimated stage by stage, not from a rate per m²
  • Labour is costed at your true hourly cost, not the wage
  • Access, skips and travel are in, and the price is cost ÷ (1 − floor)
  • Hidden timber has a rate; VAT and payment terms are in writing
FAQ

Frequently asked questions

How do you price a roofing job?

Measure the true roof area, take off the materials with 10 to 15% for waste and cuts, estimate the hours for each stage (set-up, strip, prepare, cover, details, clean-up) at your true hourly cost, add scaffold or tower, skips and travel, then divide by (1 − your margin floor). Check the total against the market, but don't build it from the market.

How much should a roofer charge per m² in the UK?

Work it out from your own costs for each roof. Cost guides give ranges such as £55 to £95 per m² for an EPDM flat roof, but small roofs carry the same set-up, skip and access costs as big ones, so their price per m² must be higher. Divide your price by the area to check it, never the other way round.

What is a typical roofer day rate in the UK?

MyBuilder's 2026 guide gives £280 to £360 a day on average, and £20 to £45 an hour, with London at £40 to £60. Use it as a check only: a day rate with materials at cost rarely covers skips, access, rain days and overheads.

How do I measure a pitched roof for a quote?

Measure the plan area the roof covers, including the overhangs, and multiply by the pitch factor: about 1.15 at 30°, 1.22 at 35°, 1.31 at 40° and 1.41 at 45°. Then add 10 to 15% to the materials for waste and cuts, more for natural slate.

What should a roofing quote include?

The roof area and covering, materials and who supplies them, access (scaffold or tower) and how long it is hired for, skips and waste, what is excluded, a rate for anything hidden such as decking or battens, the VAT treatment, the payment terms and how extra work is priced and agreed.